FIRST CONCRETE POURED AT KWINANA SWIFT SITE.
856 Views
 

 

 FIRST CONCRETE POURED AT KWINANA SWIFT SITE.

 
10.09.09
 
Congratulations to all involved in the massive effort which allowed a continuous pour of 520 cubic meters of concrete at the Kwinana Swift site on Tuesday morning.
 
30 tonnes of reinforced steal held the pads foundations together as site crew successfully poured from 2am Tuesday morning till mid afternoon.
 
The pads are the foundations for the PWPS FT8 Gas Turbines which are expected to arrive in Perth in January.
 
Earlier in the set up CTEC staff used state of the art technologies to laser align embedment’s which require millimetre accuracy for when the Gas Turbines are fitted.
 
The concrete was sourced from local concrete batching plant utilising BGC services.
 
The second pour is scheduled to start tonight and finish tomorrow arvo.

 

 
 
 SEARCH


 SUBSCRIBE

 NEWS
FIRST FIRE AT KWINANA SWIFT POWER STATION

First fire in Gas Turbine 2 at the Kwinana Swift Power Station marks the completion of the cold commissioning for the Gas Turbines.

read more -->
FIRST FUEL ARRIVES AT KWINANA SWIFT POWER STATION

Thursday 20th May at 6pm CTEC site crew received the first shipment of 50,000L of diesel fuel oil which will be used to power the 2 FT8-3 Swiftpac Gas Turbines at the Kwinana Swift Power Station.

read more -->
GT’S ARRIVE AT KWINANA SWIFT SITE AS CREW REACH 25,000 LTI FREE MILESTONE

CTEC reached project milestone  on the 20th February, with the arrival of 2 Pratt and Whitney Power Systems (PWPS) SwiftPac Gas Turbines (GT’s) at the Kwinana Swift Power Station site.