FIRST CONCRETE POURED AT KWINANA SWIFT SITE.
722 Views
 

 

 FIRST CONCRETE POURED AT KWINANA SWIFT SITE.

 
10.09.09
 
Congratulations to all involved in the massive effort which allowed a continuous pour of 520 cubic meters of concrete at the Kwinana Swift site on Tuesday morning.
 
30 tonnes of reinforced steal held the pads foundations together as site crew successfully poured from 2am Tuesday morning till mid afternoon.
 
The pads are the foundations for the PWPS FT8 Gas Turbines which are expected to arrive in Perth in January.
 
Earlier in the set up CTEC staff used state of the art technologies to laser align embedment’s which require millimetre accuracy for when the Gas Turbines are fitted.
 
The concrete was sourced from local concrete batching plant utilising BGC services.
 
The second pour is scheduled to start tonight and finish tomorrow arvo.

 

 
 
 SEARCH


 SUBSCRIBE

 NEWS
GT’S ARRIVE AT KWINANA SWIFT SITE AS CREW REACH 25,000 LTI FREE MILESTONE

CTEC reached project milestone  on the 20th February, with the arrival of 2 Pratt and Whitney Power Systems (PWPS) SwiftPac Gas Turbines (GT’s) at the Kwinana Swift Power Station site.

read more -->
CTEC WINS O&M EXTENSION AS CREW REACHES 300,000 SAFE MAN HOURS

CTEC officially awarded a 2 year extension on the Gardabani Power Station Operations and Maintenance Contract as crew reach 300,000 safe mans hour’s accident free.

read more -->
AWARDED TENDERERS ANNOUNCED

Construction of the 120 MW Kwinana Swift Power Plant is progressing strongly, keeping to schedule and on budget.